After another 250 Km long journey by truck to their final destination in Acindar’s Villa Constitucion plant, the erection process was started. Both MultiServ and E-Crane have an experienced team on site to assure a smooth and safe installation.

Mr. Francois Schaeffer (Project Manager MultiServ) and Mr. Lieven Bauwens (Managing Director E-Crane) witnessing the loading of the components at the port of Zarate. In order not to disturb the operations of the terminal and to secure a timely arrival at the jobsite, the bigger E-Crane® assembly groups (packages) were loaded during night time!
First components are lifted in place by our on site E-Crane erection team (Guido Van Hoecke, Luc Keysabyl and Geert Landuyt). It goes without saying that the project scale and project complexity require a perfect coordination and cooperation between all parties involved. When it comes to transport and installation of our products, E-Crane generally offers its customers an all-in-one package, including all services ranging from multi-modal transport to transport insurance.

The cranes for MultiServ were shipped as assembly groups (pre-assembled sets of components) offering maximum flexibility during transport.
E-Crane would like to thank Mr. Francois Schaeffer, Mr. Benoit Mathieu and Mr. Ricardo Fiorotto for their “can-do” attitude and their help and advice with the reception of the cranes in Argentina.